COMPONENT LOCATION
GENERAL DESCRIPTION

One terminal of main relay is connected to battery and the other terminal which is ground point is conneted to PCM. PCM monitors the voltages flowing into main relay and going through it.

DTC DESCRIPTION

Checking the contolling state of main relay every 10 sec. under detecting condition, if open or short in the circuit is detected for more than 5 sec., PCM sets P0685.

DTC DETECTING CONDITION

Item

Detecting Condition

Possible cause

DTC Strategy

Detects a short to ground, to battery or open circuit on Main Relay output Fault information provided by an output driver chip.

Poor Connection

Open or short in control circuit.

Main Relay

PCM

EnableConditions

Engine Running

11V ≤ Ignition Voltage ≤ 16V

Enable Time delay ≥ 0.5sec.

Threshold value

Open or Short

DiagnosisTime

Contineous

(More than 5sec. Failure for every 10 sec. test)

MIL On Condition

DTC only (NO MIL ON)

SPECIFICATION

Coil Resistance

70Ω ~ 120Ω

SCHEMATIC DIAGRAM
MONITOR SCANTOOL DATA
1.

Connect scantool to DLC(Data Link Connector)

2.

Warm up the engine to normal operating temperature.

3.

Monitor "Main Relay" parameter on scantool.

4.

Is the "Main Relay" parameter displayed correctly ?

▶ Fault is intermittent caused by poor contact in Sensor’s and/or PCM’s connector or was repaired and PCM memory was not cleared. Thoroughly check connectors for looseness, poor connection, bending, corrosion, contamination, deterioration, or damage. Repair or replace as necessary and go to "Verification of Vehicle Repair" procedure

▶ Go to "Terminal and Connector Inspection" procedure.

TERMINAL AND CONNECTOR INSPECTION
1.

Many malfunctions in the electrical system are caused by poor harness and terminals. Faults can also be caused by interference from other electrical systems, and mechanical or chemical damage.

2.

Thoroughly check connectors for looseness, poor connection, bending, corrosion, contamination, deterioration, or damage.

3.

Has a problem been found?

▶ Repair as necessary and go to "Verification of Vehicle Repair" procedure

▶ Go to " Power Circuit Inspection " procedure.

POWER CIRCUIT INSEPCTION
1.

IG "OFF"

2.

Disconnect Main Relay

3.

IG "ON" & ENG "OFF".

4.

Measure voltage between harness terminal 2 of Main Relay and chassis ground.

5.

Measure voltage between harness terminal 5 of Main Relay and chassis ground.

Specification : B+

6.

Is the measured voltage within specification ?

▶ Go to "Control Circuit Inspecition" procedure.

▶ Check fuse between battery and main relay is disconnected.

▶ Repair or replace open or short in harness and then go to "Verification of Vehicle Repair" procedure.

CONTROL CIRCUIT INSPECTION
1.

Check short in coil control

(1)

IG "OFF".

(2)

Disconnect Main Relay and PCM connector.

(3)

Measure resistance between harness terminal 4 and chassis ground.

(4)

Measure resistance between harness terminal 4 and 5 of Main Relay.

Specification : Infinite

(5)

Is the measured resistance within specification ?

▶ Go to "Check open in coil control" as follows.

▶ Repair or replace as necessary and then go to " Verification of Vehicle Repair" procedure.

2.

Check open in coil control

(1)

IG "OFF".

(2)

Disconnect Main Relay and PCM connector.

(3)

Measure resistance between harness terminal 4 of Main Relay and harness terminal 43 of PCM harness connector.

Specification : Approx. below 1Ω

(4)

Is the measured resistance within specifications ?

▶ Go to "Component Inspection" procedure.

▶ Repair or replace as necessary and then, go to "Verification of Vehicle Repair" procedure.

COMPONENT INSPECTION
1.

Check Main Relay

(1)

IG "OFF"

(2)

Disconnect Main Relay

(3)

Measure resistance between terminal 5 and 3 of Main Relay

(4)

Measure resistance between terminal 4 and 2 of Main Relay.

Specification :

Terminal

continuity

3 ~ 5

NO

2 ~ 4

YES (Approx. 70Ω ~ 120Ω)

(5)

Is the measured reisistance within specification ?

▶ Substitute with a known - good PCM and check for proper operation.

If the problem is corrected, replace PCM and go to "Verification of Vehicle Repair" procedure.

note

There is a memory reset function on scantool that can erase optional parts automatically detected and memorized by PCM.

▶ Substitute with a known - good Main Relay and check for proper operation.

If the problem is corrected, replace Main Relay and go to "Verification of Vehicle Repair"procedure.

VERIFICATION OF VEHICLE REPAIR

After a repair, it is essential to verify that the fault has been corrected.

1.

Monitor and record the Freeze Frame Data for the Diagnostic Trouble Code(DTC) which has been diagnosed.

2.

Using a Scantool, Clear the DTCs

3.

Operate the vehicle within conditions noted in the freeze frame data or enable conditions

4.

Monitor that all rediness test have been verified as " Complete "

5.

Are any DTCs present ?

▶ Go to the applicable troubleshoooting procedure.

▶ System is performing to specification at this time.