Inspection
1.

Measure the pressure of high pressure line by measuring voltage output between terminal “1” and “2”.

2.

Inspect the voltage value whether it is sufficient to be regular value or not.

Vout = 0.254929 * P + 0.1

3.

If the measured voltage value is not specification, replace the A/C pressure transducer.

Replacement
1.

Disconnect the negative (-) battery terminal.

2.

Recover the refrigerant with a recovery/charging station.

3.

Disconnect the A/C pressure transducer connector (A).

4.

Remove the A/C pressure transducer (A).

Tightening torque:

10~12 N.m (1.0~1.2 kgf.m, 7.4~8.8 lb-ft)

caution

Take care that liquid & suction pipe are not bent.

5.

Install in the reverse order of removal.

note

When installing, replace with new O-ring (A).

Яндекс.Метрика