The daytime running unit (A) is integrated in the I/P Junction box.
Check that the light operate according to the following timing chart.
Operation condition
DRL ON
- ALT L signal and IGN2 signal input |
DRL operation
- The head lamp low beam and tail lamp ON. |
DRL OFF
- Tail lamp SW ON. |
If the daytime running light is not operated well, Inspect the connector and terminals to be sure they are all making good contact.
If the terminals are bent, loose or corroded, repair them as necessary, and recheck the system.
If the terminals look OK, go to step 4.
Make these input tests at the connector by using ETM.
If any test indicates a problem, find and correct the cause, then recheck the system.
If all the input tests prove OK, the I/P (Instrument panel) junction box must be faulty; replace it.